Calculate Planned Value
Result—
Formula
Planned % Complete × Budget at CompletionExcel formula
=B2*C2
Power BI DAX measure
Planned Value =
[Planned Percent Complete] * [Budget at Completion]
Enter your values to calculate Planned Value. Use the formula and examples below for Excel, Google Sheets, Power BI, and dashboards.
Useful learning resources related to this page. As an Amazon Associate, this site may earn from qualifying purchases at no extra cost to you.
Planned % Complete × Budget at Completion=B2*C2
Planned Value =
[Planned Percent Complete] * [Budget at Completion]